Twenty-Three Years A construction chronicle
Chronicle · Six chapters · 2026

A national museum, built across a generation. The chronicle.

The Grand Egyptian Museum took twenty-three years to build, from the site selection of 2002 to the opening night of November 2025. A construction-history journal, written from the public record, the trade press, and the archival photographs of the works.

Twenty-Three Years — A Construction Chronicle of the GEM
Above — Twenty-Three Years, opening roomsPhotograph: Wikimedia Commons (CC)
29°59'N · 31°08'E 2002 → 2025 · One site · One building Independent · Non-commercial · Reader-supported by letter
The chronicle

Six chapters from a long building.

Each chapter is a phase of the works — site selection, competition, first phase, main contractor, the COVID interruption, the opening — written from the trade press, the official communiqués, and conversations on the site itself.

The site selection of 2002
Chapter 01 · Site12 min · 2002

The site selection of 2002

The site selection of January 2002, on a fifty-hectare parcel two kilometres from the Khufu pyramid, was the first public act of the project. The choice of site — outside the existing archaeological zone, but within sight of the pyramids — established the building's argument before a single drawing was made.

Read the field report →
The international competition of 2003
Chapter 02 · Competition13 min · 2003

The international competition of 2003

The competition opened in January 2002 and closed in June 2003 with 1,557 entries from eighty-three countries. The winner — Heneghan Peng, a five-person practice in Dublin — was announced in a press conference at the Manial Palace in late June, in the Egyptian summer heat.

Read the field report →
The first phase, 2010-2014
Chapter 03 · First phase12 min · 2010-14

The first phase, 2010-2014

The first phase of construction — site preparation, foundations, the conservation centre — ran from 2010 to 2014 under a Belgian-Egyptian joint venture. The conservation centre opened first, in 2010, three years before any work began on the main museum building itself.

Read the field report →
The main contractor and the long middle, 2014-2020
Chapter 04 · Main works14 min · 2014-20

The main contractor and the long middle, 2014-2020

The main building contract was awarded in 2014 to a Belgian-Egyptian joint venture working from a site office at the south of the parcel. The long middle of the project — six years of cladding, structure, services, internal fit-out — is the least photographed and the least written about phase of the works.

Read the field report →
The interruption of 2020 and the slow restart
Chapter 05 · COVID11 min · 2020-22

The interruption of 2020 and the slow restart

In March 2020 the works paused. The site went quiet for the better part of a year, with a skeleton crew on the conservation centre and the main building dark behind its scaffolding. The restart, in late 2021, was slow and was complicated by the global supply problems of the period.

Read the field report →
Hossam Abdel-Rahman
// The author

Hossam Abdel-Rahman — Construction-history journalist, Giza.

Trade reporter for the Egyptian construction press, twenty-six years on the beat. Lives a kilometre from the GEM site and watched the cladding go on, course by course, from his balcony. More on the project →